This project consists of ramp revisions, intersection and frontage road operational improvements between FM 2252 and Schwab Road in New Braunfels.
Need & Purpose
Improve safety and mobility
Project Description
Operational improvements at FM 2252, FM 1103 and Schwab Rd consisting of the construction of new entrance and exits ramps both northbound and southbound on I-35.
Construction of a VIA Park and Ride facility both NB and SB between FM 1103 and Schwab Rd on the sites of the old Rest Areas.
Funding
Construction cost: $24.6 million
Schedule
Construction began in July 2019 and is expected to be completed in 2022.