I-35 at Northwest Boulevard

Overview:

The City of Georgetown project consists of the construction of a four-lane roadway with a roundabout and intersection improvements, a four-lane bridge over I-35, utility improvements and storm water and water quality controls from Fontana Boulevard to Austin Avenue. The purpose of the project is to reduce congestion and delays, improve safety along Northwest Boulevard and Williams Drive and to provide access to Austin Avenue and San Gabriel Park.

Need & Purpose
  • Improve safety and mobility
Project Description
  • Construction of a four-lane roadway from Fontana Boulevard to Austin Avenue
  • Construction of a roundabout and intersection improvements
Funding
  • Project development funded by the City of Georgetown
  • Construction funded by the City of Georgetown
  • Construction cost: $8.15 million
Schedule
  • Finalized schematic and environmental documentation: Complete
  • Begin Plans, Specifications and Estimates (PS&E): January 2014
  • Complete PS&E: March 2019
  • Construction letting: April 2019
  • Construction start: September 2019
  • Construction completion: anticipated fall 2020