I-35 at Westinghouse Road

Overview:

This project consists of replacing the existing interchange configuration at I-35 and Westinghouse Road and constructing a new partial Continuous Flow Intersection (CFI). Currently, the I-35 mainlanes go under Westinghouse Road. The new configuration would have the I-35 mainlanes going over Westinghouse Road.

Need & Purpose
  • Improve safety and mobility
Project Description
  • Demolish the existing Westinghouse Road bridge and construct a new I-35 bridge over Westinghouse Road
  • Construct a westbound to southbound Continuous Flow Intersection (CFI) at Westinghouse Road
  • Improve bicycle and pedestrian sidewalks and paths
Funding
  • Project development funded by TxDOT
Schedule
  • Finalized schematic and environmental documentation: anticipated winter 2020
  • Begin Plans, Specifications and Estimates (PS&E): anticipated winter 2020
  • Complete PS&E: anticipated spring 2023
  • Construction letting: anticipated summer 2023
  • Construction start: anticipated summer 2023
  • Construction completion: anticipated winter 2025
Downloads

Project Vicinity Map

I-35 at Westinghouse Road

Contact

Public Information Officer

TxDOT Austin District
P.O. Box 15426
Austin, TX 78761-5426

(512) 832-7000

Email