My35 Central Texas News

September 2015
Contact
Jodi Wheatley
I-35 Information Specialist
TxDOT Waco District
100 S. Loop Dr.
Waco, TX 76704
254-867-2836
Contact My35
Calendar
Future Events Being Planned

We're now scheduling evening project-update meetings for the communities along I-35. If you'd like to have one in your area, call us and we'd be glad to get it set up for you.

Helping Wrong-way Drivers See the Right Path

With the most highway lane miles in the country, it's no surprise that Texas leads the nation in the number of wrong-way crashes — crashes that occur when a driver heads the wrong direction on a roadway and into oncoming traffic. Every year since 2010, about 800 wrong-way crashes have occurred in Texas. That number spiked to 989 last year. So far in 2015, 621 wrong-way crashes have been reported across the state, resulting in 51 deaths. | Read More

Sign Up to Avoid Traffic Delays: Alternate Route Information Now Available for I-35 Motorists When Incidents Occur

In a significant improvement to traveler-information outreach in the Waco District, TxDOT will now be able to inform I-35 motorists if an alternate route is suggested or a detour (a required re-routing) has been set up, when incidents occur along the interstate. | Read More

Speed Limit Study Under Way Near Temple

Beginning this month, I-35 motorists traveling south near Loop 363 in Temple may notice speed limits posted directly onto the pavement, just as the work zone begins. This manner of displaying the 60 mph speed limit is part of a research project, but it could become routine for the TxDOT Waco District, if it is found to be effective. | Read More

Construction updates

Section 1B: SALADO (FM 2843 to FM 2484)

Access this section's project map (schematic).

lane closures
  • The old southbound access road is closed permanently from Thomas Arnold Rd. (exit #284) to FM 2268 (exit #283), due to extensive flood damage at Salado Creek during the May storms. Traffic needing to access the FM 2268/Holland Rd. bridge will cross to the northbound side and turn right on the access road (changed temporarily to two-way) to FM 2268 and turn right to cross back over to the southbound side. This detour will remain in effect until the new southbound access road is constructed over the creek.
Milestones
  • Finished setting beams on the new southbound mainlane bridge over Salado Creek.
  • Completed laying final asphalt surface on the northbound frontage road from FM 2484 in Salado to Loop 121 in Belton. (It will remain a one-lane roadway until final striping of the pavement can be completed.)
  • Completed final asphalt surfacing of the new Thomas Arnold bridge.
  • Installed additional signage north and south of Salado.
Down the Road
  • Continue constructing the northbound mainlane north of Main St. to the end of the project.
  • Complete the FM 2268 southbound exit ramp.
  • Begin paving the new southbound mainlanes between the FM 2268 exit ramp and Salado Creek.
  • Continue constructing the retaining walls at FM 2484.
  • Continue constructing the retaining walls between Salado Creek and Thomas Arnold along the mainlanes.
  • Continue constructing the southbound frontage road north and south of FM 2484.
  • Continue constructing the final southbound mainlane segment from Thomas Arnold south to the end of the project.
  • Continue constructing the new Salado Creek mainlane bridge segment.
  • Continue to seed and sod along the frontage roads.
  • Pave the Thomas Arnold Rd. connection and add sidewalks at frontage-road intersections.

Section 1C: Salado to belton (FM 2484 to us 190/fm 436)

Access this section's project map (schematic).

Milestones
  • Completed laying the final asphalt surface on the southbound frontage road from FM 2484 in Salado to Loop 121 in Belton. (It will remain a one-lane roadway until final striping of the pavement can be completed.)
  • Installed additional new wayfinding signage along northbound mainlanes.
Down the road
  • Continue constructing the southbound mainlanes and culverts from FM 2484 to Loop 121.
  • Continue constructing the southbound frontage road from Loop 121 to FM 2484.
  • Continue the intersection construction at Loop 121 and the frontage roads.
  • Continue constructing the US 190 direct connect/flyover.
  • Continue constructing the ramp from the northbound mainlanes to the US 190 direct connect/flyover.
  • Complete installation of traffic signals at the intersection of FM 436/US 190 and the frontage roads and prepare to activate.
  • Continue installation of traffic signals at the intersection of Loop 121 and I-35.
  • Complete the signal work and have the signals operational.
  • Continue to sod along the northbound mainlanes and frontage road.

SECTION 2B: TEMPLE (S. LOOP 363 TO N. LOOP 363)

Access this section's project map (schematic).

milestones
  • Began constructing the new off-ramp south of Loop 363.
  • Began constructing the embankment header for the east side of the Spur 290 underpass.
  • Began installing drill shafts for the east abutment at the Spur 290 underpass.
  • Began grading and installing PCP panels on the southbound frontage-road BNSF Lampas-Sub railroad-bridge overpass.
Down the Road
  • Continue constructing new off-ramp south of Loop 363.
  • Continue installing culverts north of S. Loop 363 across the northbound frontage road, off ramp, and mainlanes.
  • Continue constructing the storm sewer on the southbound and northbound frontage roads north of Nugent throughout the project.
  • Continue building the bridge abutments and interior columns at Spur 290.
  • Continue the concrete paving on Spur 290.
  • Continue constructing the southbound frontage road bridges at BNSF Railroad's Belco and Lampas-Sub lines.
  • Continue constructing the retaining wall on the northbound frontage road by Carpenter's and the BNSF Railroad underpass.
  • Continue constructing the retaining wall on the southbound frontage road at Spur 290 underpass.
  • Continue constructing the retaining walls on the southbound frontage road at the BNSF Railroad overpass.
  • Continue constructing the embankment header for the east side of Spur 290.
  • Continue installing drill shafts for east abutment at the Spur 290 underpass.
  • Continue grading and installing PCP panels on the southbound frontage-road BNSF Lampas-Sub Bridge Overpass.

Section 3A-1: TEMPLE TO TROY (N. LOOP 363 TO N. TROY CITY LIMIT)

Access this section's project map (schematic).

Milestones
  • Traffic switched onto the new southbound frontage road for the entire length of the project.
  • Started pouring columns and drill shafts for the southbound mainlane bridge at North Troy.
Down the Road
  • Begin concrete pavement on the northbound frontage road between Berger/Hart Rd. and FM 1237.
  • Finish removing and salvaging material from the existing southbound frontage road.
  • Continue work on Church Avenue and begin working on driveways.
  • Complete pavement section on the northbound frontage road between FM 1237 and FM 935.
  • Complete all drill shafts and columns for the southbound mainlane bridge at North Troy.
  • Continue building new northbound mainlanes between Big Elm Rd and Old Blevins Rd.

Section 3A-2: TROY to bruceville-eddy (N. TROY CITY LIMIT to woodlawn rd.)

Access this section's project map (schematic).

Down the Road
  • Finish concrete paving on the new northbound mainlane from FM 107 to UPRR.
  • Begin asphalt paving on the northbound frontage road at UPRR.
  • Continue working on the new UPRR bridges.
  • Continue constructing a retaining wall at the northbound frontage-road bridge.
  • Continue concrete paving on the southbound frontage road from UPRR to FM 107.
  • Continue working on the northbound mainlanes from FM 107 to UPRR.

Section 3B: LORENA TO HEWITT (WOODLAWN RD. TO SUN VALLEY BLVD./FM 2063)

Access this section's project map (schematic).

MILESTONES
  • Switched traffic to new concrete pavement in the left lane of the southbound frontage road from Sun Valley Blvd. to Moonlight Dr.
  • Began construction on the right lane of the southbound frontage road from Sun Valley Blvd. to Moonlight Dr., and all of the driveways in this area.
  • Completed construction of the new on- and off-ramps on the southbound side, from Sun Valley Blvd. to Moonlight Dr.
  • Switched southbound frontage-road traffic onto the new North Cow Bayou bridge.
Down the Road
  • Complete excavation for the Telephone Rd. bridges and begin construction on the remaining half of the new bridge.
  • Begin construction of the southbound frontage-road bridge at South Cow Bayou.
  • Finish constructing the south-to-north turnaround bridge at W. FM 2837.
  • Begin construction of concrete cantilevered sign supports.
  • Begin installation of highway illumination.
  • Begin constructing the retaining wall for the Telephone Road bridge.
  • Begin constructing the southbound mainlane through Lorena.
  • Begin constructing the southbound mainlane from Woodlawn to south end of the job.

BRAZOS RIVER BRIDGES (WACO)

Access this section's project map (schematic).

Milestones
  • Completed installation of underpass lighting.
  • Began landscaping along the river.
Down the Road
  • Begin installation of railing along the new sidewalk areas under the bridge.
  • Continue landscaping along the river.
  • Overall job completion and clean up.

Section 4A: WACO ACCESS ROADS (MLK TO TAYLOR)

Access this section's project map (schematic).

Lane Closures
  • North-to-south access roads and the turnaround from MLK Blvd. under I-35 at the UPRR crossing have been permanently closed. New access roads and railroad crossing bridges will be constructed to replace them.
  • The southbound frontage road turnaround between Forrest St. and UPRR has been closed permanently at Cherry St.
milestones
  • Began building the retaining wall south of the new southbound frontage-road bridge over UPRR.
  • Began installing temporary shoring on the northeast side of UPRR.
Down the Road
  • Continue building the retaining wall south of the new southbound frontage-road bridge over UPRR.
  • Continue to install drainage structures at MLK.
  • Continue installing temporary shoring on the northeast side of UPRR.

Section 5A: WACO TO WEST (N. LOOP 340 TO FM 1858)

Access this section's project map (schematic).

Milestones
  • Completed installation of traffic signals at FM 308.
Down the Road
  • Continue installing traffic signs and illumination.
  • Work on "punch list" of minor tasks to be completed.

Section 5B: WEST TO ABBOTT (FM 1858/TOKIO RD. TO FM 1304)

Access this section's project map (schematic).

Down the Road
  • Complete project lighting.
  • Continue installing traffic signals.
  • Continue seeding and landscaping.
  • Work on "punch list" of minor tasks to be completed.