We're now scheduling evening project-update meetings for the communities along I-35. If you'd like to have one in your area, call us and we'd be glad to get it set up for you.


Sign up for My35 Main Street News

TxDOT Heavy Equipment Operators: Is This Job Right For You?

It may be a cliché, but it's still true that big trucks fascinate many people. Social media often features photos of small boys enthralled by big trucks working nearby. And there's even a heavy equipment playground for grownups called "Dig This" in Las Vegas, Nevada, that (for a fee) lets grown-ups operate bulldozers, loaders and excavators for fun. | Read More

Construction updates

Section 2B: TEMPLE (S. LOOP 363 TO N. LOOP 363)

Access this section's project map (schematic).

Down the Road
  • Continue constructing the northbound mainlanes and northbound frontage road overpasses at the BNSF Belco Yard railroad.
  • Continue constructing northbound mainlane pavement from Adams and Central Ave. Interchange north to the BNSF Belco Yard overpasses.
  • Continue constructing northbound mainlane pavement from BNSF Belco overpass north through the remainder of the project.
  • Continue installation of retaining wall No. 1.
  • Continue construction of the BNSF underpass.
  • Continue construction of the BNSF Lampasas Sub northbound mainlane overpass.
  • Continue construction of Retaining Wall 52 north of Nugent Ave.
  • Continue construction of the west side of the Adams/Central Ave. Interchange.

Section 3A-1: TEMPLE TO TROY (N. LOOP 363 TO N. TROY CITY LIMIT)

Access this section's project map (schematic).

MILESTONES
  • Completed paving the south-to-north turnaround at the North Troy intersection.
  • Completed paving the north-to-south turnaround at the Berger/Hart Rd. intersection.
  • Completed paving the north-to-south turnaround at North Troy intersection.
  • Completed pouring the asphalt for the northbound frontage road north and south of the FM 1237 intersection.
  • Opened crossing at FM 1237/Pendleton Rd. to one lane in each direction.
Down the Road
  • Complete installing signs for the new southbound mainlanes.
  • Continue working on the east half of the northbound frontage road from FM 935 to North Troy.
  • Continue working on the northbound frontage road between Berger/Hart Rd. and FM 1237.
  • Continue working on the North Troy intersection, Berger/Hart Rd. intersection, FM 1237 intersection and West Main Street/FM 935.
  • Switch traffic at northbound mainlanes and mainlanes north of Berger/Hart Rd. to the outside and middle lanes.
  • Begin pouring the permanent central barrier wall at the mainlanes north of Berger/Hart Rd.

Section 3A-2: TROY to bruceville-eddy (N. TROY CITY LIMIT to woodlawn rd.)

Access this section's project map (schematic).

mILESTONES
  • Opened the new Big Elm Rd. intersection with one lane open in each direction.
  • Switched traffic onto new concrete paving on southbound mainlane pavement between Big Elm Rd. and Big Elm Creek.
  • Poured the deck for the new southbound mainlane bridge over Big Elm Creek.
  • Set beams and poured the bridge deck for the new southbound mainlane bridge over Big Elm Creek.
  • Began constructing new drainage structures along the northbound frontage road between Old Blevins Rd. and FM 107.
  • Began work on the new northbound mainlane pavement between North Eddy and Old Blevins Rd.
Down the Road
  • Continue construction on the new southbound frontage road at FM 107.
  • Continue paving the northbound frontage road between Old Blevins Rd. and FM 107.
  • Continue constructing new drainage structures along the northbound frontage road between Old Blevins Rd. and FM 107.
  • Continue working on the east retaining wall at the new FM 107 underpass.
  • Continuing working on the west retaining wall rail and riprap placement.
  • Continue paving the southbound mainlanes between North Eddy and Old Blevins Rd.
  • Continue constructing new drainage structures along the northbound frontage road between Old Blevins Rd. and FM 107.
  • Continue placing concrete paving on southbound mainlane pavement between Big Elm Rd. and Big Elm Creek.
  • Begin working on remainder of southbound pavement.
  • Continue working on rail for the new southbound mainlane bridge over Big Elm Creek.
  • Continue building additional lanes and turnarounds at Big Elm Rd.
  • Continue working on the new intersection of the northbound frontage road and FM 107.
  • Complete new northbound pavement from the railroad to the north end of project.

SECTION 4A: WACO ACCESS ROADS (MLK TO TAYLOR)

Access this section's project map (schematic).

LANE CLOSURES
  • North-to-south access roads and the turnaround from MLK Blvd. under I-35 at the UPRR crossing have been permanently closed. New access roads and railroad crossing bridges will be constructed to replace them.
  • The southbound frontage road turnaround between Forrest St. and UPRR has been closed permanently at Cherry St.
  • Forrest St. Bridge is closed.
milestones
  • Completed construction of new Forrest St. bridge drill shafts.
Down the Road
  • Continue construction of the northbound and southbound frontage-road bridge rails.
  • Continue to work on opening the new frontage roads.
  • Continue construction of new Forrest St. bridge (currently working on drilled shafts).
  • Continue to work on tie-in point for the new southbound frontage road to the existing frontage road.
  • Construct the new northbound on-ramp from MLK Blvd.
  • Complete northbound and southbound bridge retaining walls at Forrest Ave. bridge.
  • Complete construction of columns in the center median for the Forrest Ave. bridge.
  • Complete building of abutments for the Forrest Ave. bridge.
  • Hang beams for the Forrest Ave. bridge.