Facilitating Pedestrian, Bicyclist Safety during Back-to-School Season

It's back-to-school season for Baylor University and Waco schools. TxDOT’s Waco District I-35 team works to keep pedestrians and bicyclists safe, especially during this busy season in the midst of the COVID-19 pandemic. | Read More

Construction Updates

Section 4B: Waco (12th Street to North Loop 340)

Access this section's project map (schematic).

Milestones

  • Completed side-street intersections along the southbound access road between 18th and 11th Streets.
  • Shift traffic onto portions of the new northbound frontage road.
  • Completed the removal of old pavement from the former northbound mainlanes.
  • Shifted traffic onto portions of the new northbound frontage road north of US 84.
  • Shifted southbound mainlane traffic onto new pavement north of US 77.
  • Completed the sound wall on the southbound frontage road.
  • Demolished the northbound mainlane bridges over MLK Boulevard, University Parks Drive, 4th/5th Streets, US 84, Behrens Circle, and the Brazos River.

Down the Road

  • Continue demolition of the bridges over the Union Pacific Railroad.
  • Continue sidewalk and driveway construction for the northbound and southbound access road from Behrens Circle to 12th Street.
  • Continue setting the northbound retaining wall.
  • Continue the east-end replacement of Culvert 5 (Waco Creek).
  • Continue tying individual inlets to the southbound stormwater trunk line.
  • Continue construction of US 84 / Waco Drive on the east side of I-35.
  • Continue northbound frontage road paving, side streets, and driveways throughout the project.
  • Continue to upgrade utilities specifically at 2nd Street at the southbound frontage road.
  • Continue removing old pavement from the former northbound main lanes.
  • Continue drill shaft operations for new northbound structures.
  • Continue columns and bent caps at University Parks Drive and MLK Boulevard.
  • Continue paving of interchanges and U-turns at Behrens Circle and other interchanges.
  • Start BUS 77 paving.
  • Begin northbound mainlane paving.
  • Begin pouring bridge decks starting at 11th/12th Streets.
  • Complete cross-street paving.
  • Continue drilled shaft foundations for traffic signals.
  • Start drilled shaft foundations for illumination.

I-35E Expansion (I-35 East/West split to Ellis County line)

Milestones

  • Completed bridge rails for the new FM 934 and FM 2959 overpasses.

Down the Road

  • Construct the Phase 3 portion of the southbound mainlanes, including earthwork and culverts.
  • Construct the I-35E southbound overpass at I-35W.
  • Construct Phase 3 concrete pavement along I-35E.
  • Complete concrete paving on FM 934, FM 2959, and related exit and entrance ramps.

Top

My35 logo

Central Texas News

Contact

Jake Smith
I-35 Public Information Officer
254-867-2705
Contact My35

TxDOT Waco District
100 S. Loop Drive
Waco, TX 76704
Calendar

Future Events Being Planned

We're now scheduling evening project-update meetings for the communities along I-35. If you'd like to have one in your area, call us and we'd be glad to get it set up for you.