Time for That Day Trip or Staycation? Plan Ahead with I-35 Safety Tips

Staying in Waco for summer vacation? Follow these tips to keep your loved ones (and yourself) safe. | Read More

Static to Streaming: View Real-Time Video through My35 Traffic Cameras

TxDOT’s I-35 Waco District team manages My35 traffic cameras for the traveling public. Cameras serve many purposes, including giving static snapshots to travelers. | Read More

Construction Updates

Section 4B: Waco (12th Street to North Loop 340)

Access this section's project map (schematic).

Milestones

  • Switched northbound mainlane traffic onto new pavement from the south end of the project to Forrest Street.
  • Continued to shift traffic onto portions of the new northbound frontage road.
  • Completed the new mainlane bridge deck at Business 77.
  • Completed paving on Hogan Lane east of the northbound frontage road.
  • Completed U-turns at 4th/5th Streets, University Parks Drive, and Martin Luther King, Jr. Boulevard.

Down the Road

  • Continue sidewalk construction for the northbound and southbound frontage roads.
  • Complete setting the northbound retaining wall.
  • Continue the east-end headwall and riprap construction of Culvert 5 (Waco Creek).
  • Continue construction and tie-ins of US 84/Waco Drive on the east side of I-35.
  • Continue grading the northbound mainlanes in preparation for new pavement.
  • Continue northbound mainlane paving.
  • Continue paving intersections and U-turns at Business 77 and 11th/12th Streets.
  • Continue cross-street paving.
  • Continue utility upgrades (specifically at 2nd Street) at the southbound frontage road.
  • Continue drilled shaft installation for new traffic signals.
  • Continue Dutton Avenue construction.

I-35E Expansion (I-35 East/West split to Ellis County line)

Milestones

  • Switched northbound I-35E traffic onto the new concrete pavement for Phase 4.
  • Completed the I-35E southbound exit to US 77.
  • Temporarily closed the northbound exit and entrance ramps at FM 934.
  • Established permanent vegetation and soil stabilization.

Down the Road

  • Construct the Phase 4 portion of the northbound mainlanes, including earthwork, culverts, paving, and bridge at White Rock Creek.
  • Complete concrete paving on FM 2959 and FM 934.
  • Construct the northbound exit and entrance ramps at FM 934 and reopen to traffic.

Top

My35 logo

Central Texas News

Contact

Jake Smith
I-35 Public Information Officer
254-867-2705
Contact My35

TxDOT Waco District
100 S. Loop Drive
Waco, TX 76704
Calendar

Future Events Being Planned

We're now scheduling evening project-update meetings for the communities along I-35. If you'd like to have one in your area, call us and we'd be glad to get it set up for you.

My35 logo

Sign up!

for My35 Main Street Texas News

©2022 Texas Department of Transportation • All Rights Reserved