Interstate 35 Expansion
- Waco Section 1 Section One of the I-35 expansion stretches from the Williamson
and Bell County line to the south and US 190 in Belton to the north.
The section is broken into three sections:
- Section A: Williamson/Bell County line to FM 2268 -
Construction is completed.
- Section B: FM 2268 to FM 2484 in Bell County -
Scheduled to be let in July 2011. The project is estimated to
cost $90.4 million and will be funded through Proposition 12
bonds. A
public hearing took place in March 2010.
- Section C: FM 2484 to US 190 in Belton - Scheduled to
be let in April 2010 and is estimated to cost $134.8 million,
funded by the American Recovery and Reinvestment Act.
Schematics
were presented at a
public hearing on June 30, 2009 and are available for review.

|
|
|