I-35 from south of Loop 82 to north of River Ridge Parkway

Overview

This project consists of new northbound I-35 ramps between Loop 82 (Aquarena Springs Drive) and River Ridge Parkway. A northbound exit ramp to River Ridge Parkway would be constructed and an existing northbound entrance ramp south of River Ridge Parkway would be relocated to provide adequate weaving distance.

Need & Purpose

  • Improve safety and mobility

Project Description

  • Construct northbound exit ramp to River Ridge Parkway
  • Relocate existing northbound entrance ramp south of River Ridge Parkway to provide adequate weaving distance
  • Reconstruct the northbound frontage road between Loop 82 and River Ridge Parkway

Funding

  • Project development funded by TxDOT
  • Construction funded by the Capital Area Metropolitan Planning Organization and TxDOT
  • Construction cost: $14 million

Schedule

  • Finalize schematic and environmental documentation: March 2017
  • Begin Plans, Specifications and Estimates (PS&E): May 2016
  • Complete PS&E: anticipated July 2020
  • Construction letting: anticipated July 2020
  • Construction start: January 2021
  • Construction completion: December 2022

Project Activity

Get Involved

Downloads

Project Vicinity Map

River Ridge Parkway to south of Loop 82 map

CONTACT

Public Information Officer
(512) 832-7000
Email

TxDOT Austin District
P.O. Box 15426
Austin, TX 78761-5426

©2022 Texas Department of Transportation • All Rights Reserved