One new ramp was added and five existing ramps were modified between RM 150 and the Blanco River.

Need & Purpose

  • Improve safety and mobility

Project Description

  • Reversed the southbound ramp configurations between RM 150 and Yarrington Road
  • Reversed the northbound ramp configuration between Yarrington Road and RM 150
  • Relocated the northbound Yarrington Road exit ramp
  • Constructed a new northbound entrance ramp at the location of the existing Yarrington Road exit ramp

Funding

  • Project development funded by TxDOT
  • Construction funded by Proposition 1
  • Construction cost: $9 million

Schedule

  • Finalized schematic and environmental documentation: July 2015
  • Begin Plans, Specifications and Estimates (PS&E): July 2015
  • Complete PS&E: December 2015
  • Construction letting: December 2015
  • Construction start: April 2016
  • Construction completion: November 2017

Downloads

Project Vicinity Map

RM 150 to Blanco River map

CONTACT

Public Information Officer
(512) 832-7000
Email

TxDOT Austin District
P.O. Box 15426
Austin, TX 78761-5426

©2022 Texas Department of Transportation • All Rights Reserved