Skip to main content

Intersection Improvements Designed to Improve Mobility, Safety for Waco Vehicles, Pedestrians, Visitors

Back to Volume 11, Number 4


On Nov. 1, TxDOT closed portions of Dutton Ave. at 4th Street in Waco to begin reconstruction of this area. With the growth of Baylor University—specifically the new Baylor Visitors Center and downtown Waco—the realignment and reconfiguration of the intersections of 4th Street, 5th Street and Dutton Avenue at the northbound frontage road are essential. Growth in the area has not only increased vehicular traffic, but also pedestrian and bicycle traffic. Additionally, the intersections need upgrades to improve accommodations for those with disabilities.

Before TxDOT began this work, they met with the Balor Athletic Department to discuss the November sports calendar. There is a parking garage on Dutton Avenue that’s heavily used during football games. TxDOT worked out the phasing such that the garage entrance and exit could stay open while construction began at 4th Street and Dutton Avenue. During November, the contractor began demolition of the old pavement, installed new drainage structures and graded the new alignment.

Dutton Avenue under reconstruction as part of the I-35 Waco Project ahead of the completion of the new Baylor University Hurd Welcome Center.


The new design of the I35 bridges over 4th and 5th Streets created room for a north to south U-turn before 5th Street on the northbound frontage road, as well as a south to north U-turn before 4th Street on the southbound frontage road. The new design realigns the 4th and 5th Street intersections at Dutton Avenue and the northbound frontage road, separating the intersections from each other. Separating them will increase mobility into, through and out of Baylor University’s campus. With the new configuration, crossing at the intersections will be easier thanks to new accessible curb ramps, marked crosswalks, lighting and pedestrian signals. There is currently a temporary crossing at 5th Street. The pedestrian crossing at 5th Street will remain open for the most part but might close as needed or the foot traffic diverted to 4th Street as construction continues. In an effort to provide updated information to pedestrians and bicyclists during construction, TxDOT has installed pavement clings ahead of crossing areas. The user can scan the QR Code on the pavement cling to pull up an online map that shows the crossings currently open or closed.

A pavement cling (left) and a sample screenshot from the online pedestrian map (right).


The temporary pedestrian crossing at 5th Street.


A map of the I-35 expansion shows the reconfiguration of Dutton Avenue at Baylor University in purple and abandoned roadways in turquoise. The new design (in purple) creates separate intersections with 4th and 5th Streets at Dutton Avenue and new U-turns under I-35.


Once TxDOT completes the work at 4th Street and Dutton Avenue and the new north to south U-turn before 5th Street, 4th Street will close under I-35. Once 4th Street is reconstructed, TxDOT will close 5th Street under I-35. The new construction is depicted in purple. The work is scheduled for completion in early 2022.

The newly constructed north to south U-turn before 5th Street.


The 5th Street realignment will provide a direct path from downtown Waco into Baylor University.


The growth of Baylor University and downtown Waco is also extending south to 11th and 12th Streets. Before I-35 construction, 12th Street was a bridge over the interstate. The new design now has 12th Street under I-35. This will increase mobility not only for vehicular traffic but for pedestrians and bicyclists as well. Having begun the work in May 2019, TxDOT anticipates completing improvements, new U-turns, sidewalks, lighting and pavement for 11th and 12th Streets in early 2023.

A map of the I-35 expansion shows (in purple) the reconfiguration of 11th and 12 Streets at the tie-in to Dutton Avenue on the westside of I-35. The new design, in purple, creates a path for those on the south end of Baylor University to travel to downtown Waco and vice versa.


Rough grading the new road connecting 12th Street on the east side of I-35 to 11th Street on the west side of I-35.


Steve James, project manager for the I-35 Waco Project, recently said, “I knew this project was going to be valuable to local and regional travelers. What I didn’t realize was all the concurrent construction that was going to take place by the City of Waco and Baylor University. This community is growing. What has really impressed me, besides the consistent progress of the I-35 contractor, is TxDOT’s willingness to be a good partner to the City of Waco and Baylor University. All three entities continue to meet with a spirit of cooperation. We all have projects and work to complete, but we are all pursuing them as one team. Looking back across my career, this work has been some of the most rewarding.”

Back to Volume 11, Number 4

My35 logo

Central Texas News

Contact

Jake Smith
I-35 Public Information Officer
254-867-2705
Contact My35

TxDOT Waco District
100 S. Loop Drive
Waco, TX 76704

©2022 Texas Department of Transportation • All Rights Reserved